皇上和公主小奶娃各种做h_国产精品久久久香蕉_上原亚衣番号_亚洲不卡免费视频

聯(lián)系方式 Contact

地址:懷來東花園鎮(zhèn)航天產(chǎn)業(yè)園緯二路2號

電話:137 0121 6722

傳真:010-60934713

郵件:hthjgy@163.com

在線QQ交談 在線QQ交談

搜索 Search

POST INSTALLATION INSPECTION PRIOR TO SYSTEM PRESSURE TEST

2012-5-23 14:48:17點擊:


A careful inspection of the entire piping system shall be made with particular emphasis on the following.

  • Are the anchors, guides and supports installed in accordance with the system drawings?

  • Is the proper pipe expansion joint in the proper location?

  • Are the pipe expansion joint flow direction and positioning correct?

  • Have all the pipe expansion joint shipping devices been removed?

  • Are all guides, pipe supports and the pipe expansion joints free to permit pipe movement?

  • If the system has been designed for a gas, and is to be tested with water, have provisions been made for proper support of the additional dead weight load on the piping and pipe expansion joint? Some water may remain in the bellows convolutions after the test. If this is detrimental to the bellows or system operation, means shall be provided to remove such water.

  • Has any pipe expansion joint been damaged during handling and installation?

  • Is any pipe expansion joint misaligned? This can be determined by measuring the pipe expansion joints' overall length, inspection of the convolution geometry, and checking clearances at critical points on the pipe expansion joint and at other points in the system.

  • Are the bellows and other movable portions of the pipe expansion joint free of foreign material?



圖文并茂效果